top of page

Clark County Airport GA Terminal/SRE Building

  • Halme Inc. was a subcontractor to Lehtola Builders on this project designed by Helms Engineering. Halme’s contract was to perform the civil site work and provide project management services for the entire project. The site work included repair of taxiway storm sewer piping, new aircraft tie downs, pavement repair, building excavation and new gravel parking.  

Sinai Distribution Improvements

  • Halme Inc. was the prime contractor on this new water system for the Town of Sinai. Kingbrook Rural Water System is the owner and DGR Engineering was the engineer for the project. The project included bringing a new water main into town from Kingbrooks existing system, install new water mains and services throughout the entire town and repairing the streets, alleys and lawns. Efriamson Electric of Bryant SD was a subcontractor on this project providing boring services.

Lake Herman State Park Sanitary Sewer System Modification

  • Halme Inc. was the prime contractor on this project to modify the existing sewer lagoons for the Lake Herman State Park. South Dakota Game, Fish and Parks is the owner and Civil Design was the engineer. The project included adding depth to the lagoon, building a new control dike, modifying the sewer piping system and a new liner. J.C. Ramsdell Enviro Services Inc. of Flandeau, SD installed the liner on this project as a subcontractor.

City of Doland Wastewater System Improvements

  • Halme Inc. was the prime contractor on a $1.45 million dollar project replacing sewer mainlines and services for the City of Doland. The project included new sewer mains 8' to 12' in depth, new sewer laterals to the property lines and repairing the ashalt surfacing. Helms Engineering was the engineer for the project. Basin Construction and Draintile Inc., Lien Transportation, and Hydro Klean were the major subcontractors on the project.

Ashton Water Storage Improvements

  •  Halme Inc. was the prime contractor on this project for the Town of Ashton, SD. The project included building an new concrete water reservoir and connects to the existing water system. Basin Construction and Draintile Inc. performed the concrete work as a subcontractor. Helms Engineering was the project engineer.

Kingbrook Rural Water System Dakota Access Pipeline Crossings

  • Halme Inc. was the prime contractor on this project for Kingbrook Rural Water System Inc. This $1.2 million dollar project was to lower Kingbrook's water pipe at the future crossings of the Dakota Access Oil Pipeline. The project was to install a bored fused PVC casing pipe 100' on either side and 10' below the future Dakota Access Pipeline. Then Halme installed new restrained joint water pipe through the casings and connected to the existing water pipe. The pipe size varied from 3" to 18". Efraimson Electric performed the boring for the project as a subcontractor. DGR Engineering was the project engineer.

South Shore Wastewater System Improvements

  • Halme Inc. was the prime contractor on this project for the City of South Shore. The project included rebuilding the existing sewer lagoons, installing a HDPE liner, new sewer forcemain, (2) new sewer lift staions, and new gravity sewer pipe in town. Northwest Linings and Geotextile Products and Efraimson Electric were subcontractors on this project. Helms Engineering was the project engineer.

HWY 28 Box Culverts

  • Halme Inc. was the prime contractor on this box culvert replacement project for the South Dakota Dept. of Transportation. The project includes 30,000 CY of roadway exc and borrow, building temporary detours, removing two 22' x 10' box culverts, replacing the box culverts with new cast in place 22' x 10' box culverts and resurfacing the road. Lehtola Builders, Asphalt Paving and Materials, Industrial Builders, Construction Signing Corp, J&N Seeding and Stockwell Engineers were subcontractors on this project. SDDOT (Huron Office) is the engineer on the project.

​​
Brookings County Structure and Approach Grading

  • Halme Inc. was the prime contractor on this bridge replacement project. The project includes removal of existing bridge, reshaping and ripraping channel, driving H-pile, concrete substructure and superstructure, and rebuilding the approaches to the bridge. The subcontractors on this project include Lehtola Builders, Bowes Construction, Guardrail Enterprises, and Traffic Solutions. Banner Associates inc. from Brookings SD is the engineer.


City Of Milbank Wellhouse #3

  • Halme Inc. was the prime contractor on this project to demo and and rebuild a new wellhouse for the City of Milbank. This project includes demo, new well pump, new well house, wellhouse piping and electrical controls. The subcontractors include Efriamson Electric, Lehtola Builders, Kranz Well and Excavationand Sweeney Controls. The engineer is Banner Associates Inc.


Cavour Lift Station and Forcemain Improvements

  • Halme Inc. was the prime contractor on this project to install a new lift station, valve vault, sewer forcemain and highway bores. Banner Associates is the project engineer. Our subcontactors include Efraimson Electric, Iowa Trenchless, and Skyview Construction.


North Industrial Ave. and Utility Improvements - Arlington Community Development Corp. 

  • Halme Inc. was the prime contractor on this project to build new infastructure for Arlington's Industrial Park Exspansion. The project includes new sewer, water and storm install along with a new lift station and building new streets with curb and gutter. The subcontractors on this project include Efraimson Electric and CVC Concrete Contractors. The engineer is Banner Associates Inc. from Brookings, SD.


Lake Poinsett East and Northeast Lake Drive Wastewater System Expansion

  • Halme Inc. was the prime contractor on this $2million project to expand the sewer system on Lake Poinsett. The project included new lagoon construction. 3 large lift stations, 60 small grinder lift stations, gravity sewer, sewer forcemain, and hookups to 122 homes. This is a project designed by Banner Associates Inc. Our subcontractors included Efraimson Electric, LL and Sons Excavating, Basin Construction and Draintile, Area Lawn Works, Aason Engineering, BX Civil and Sweeney Controls.


Florence Water System Improvements

  • Halme Inc. was the prime contractor on this $2million project to completely rebuild the water system for the Town of Florence SD. The project included a new well house and pumps, a new water tank, all new distribution water main and services, and rebuilding the streets after the pipe was installed. Helms Engineering of Aberdeen SD was the engineer. Our subcontractors include Efraimson Electric, Lehtola Builders, Great Plains Structures, Duininick Inc., Construstion Signing Corp. and Area Lawn Works


Astoria Wastewater System Improvements​

  • Halme Inc. was the prime contractor on this project to build an new wastewater lagoon and install a lift station. The engineer for the project was Banner Engineering. The subcontractors were Efraimson Electric, Area inc. and Lehtola Builders.

Conde Water System Improvements

  • Halme Inc. was the prime contractor on this $2.2 million project to completely rebuild the water system for the Town of Conde, SD. The project included a new well house and pumps, a new water tank, all new distribution water main and services, and rebuilding the streets after the pipe was installed. Helms Engineering of Aberdeen SD was the engineer. Our subcontractors included Efraimson Electric, Lehtola Builders, Great Plains Structures, Lien Transportation and Glacial Lakes Erosion Control.

Agropur Cheese Plant Expansion

  • Halme Inc. was a subcontractor to Miron Contruction on this $2.3 million project designed by E.A. Bonelli & Assoc. along with ISG.  Halme's contract was to perform the site work which included storm sewer piping, waste water piping, mass excavation, building excavation, parking lots, and general site preparation.  Halme utilized GPS on their equipment with this project to provide precise site prep and grade control.

Agropur Outfall Line

  • Halme Inc. was the prime contractor on this $3.4 million project for the Agropur cheese plant in Lake Norden, SD.  There was 14 miles of 16" pipe to install, along with 35 Air Release Valves.  Halme utilized GPS on their equipment to provide precise pipe depth and location.  The project also included boring under existing roads as well as an outfall structure located at the Big Sioux River.  Banner Associates of Brookings, SD was the project engineer.  Efraimson Electric of Bryant, SD, Lehtola Builders and Area, Inc. both of Lake Norden, SD were subcontractors on this project.

Kingbrook Rural Water System Expansion

  • Halme Inc. was the prime contractor on this $9.6 million project for Kingbrook Rural Water System.  There was 178 miles of rural water pipe to install ranging in sizes from 1 1/2" to 16", along with 240 services.  The project also included boring under existing roads.  The project engineer was DGR Engineering.  Efraimson Electric of Bryant, SD and Basin Construction of Hayti, SD were subcontractors on this project.

SDDOT Madison Hwy 34 Urban Reconstruction Project

  • Halme Inc. was a subcontractor to D&G Concrete Construction, Inc. on this $2.1 million project for the SDDOT.  Halme's portion of the contract was to remove and replace watermain, sanitary and storm sewer along the length of the project.  Watermain pipe sizes range from 4" to 10"; sanitary sewer pipe sizes range from 6" to 18"; and storm sewer pipe sizes range from 18" to 54".  Halme also utilized GPS on their equipment to provide precise pipe depth and grade control.

Garfield Dairy

  • Halme Inc. was a subcontractor to Riverview, LLP on this $4.6 million project.  Halme performed all of the site work, and utilized their GPS to provide precise site prep.  With retention basins, a large holding barn, milk parlor, feed pad and more, there was over 750,000 cubic yards of material to move.

Lake Norden Wellfield and Raw Water Transmission

  • Halme Inc. was the prime contractor on this project for the City of Lake Norden.  There was approximately 7,800 lineal feet of 10" water main to be installed, along with the construction of three new wells and multiple directionally drilled road and stream crossings.  Banner Associates were the engineers on this project.  Efraimson Electric of Bryant, SD, Kaiser Well Drilling of Lake Norden, SD and Guardrail Enterprises of Chancellor, SD, and Ellingson Drainage of West Concord, MN were subcontractors on this project.

Bryant Area Commercial Development - Phase 1 (Lee Street)

  • Halme Inc. was the prime contractor on this $438,000 project for the City of Bryant.  Halme rebuilt approximately 1,200 feet of street, and installed approximately 1,165 lineal feet of 8" sanitary sewer main and 1,790 lineal feet of 6" water main.  The engineer on this project was Clark Engineering.

Clark Rural Water System - Willow Lake and Bradley Improvements

  • Halme Inc. was the prime contractor on this $1.5 million project for Clark Rural Water System.  There was approximately 11.5 miles of 6" water main, 6 miles of 8" water main and approximately 1 mile of 10" water main installed.  The project also included directionally drilling under existing roads and streams.  The project engineer was Banner Associates.  Efraimson Electric of Bryant, SD and Guardrail Enterprises of Chancellor, SD were subcontractors on this project.

Elkton Utility Improvements - Phase I

  • Halme Inc. was the prime contractor for the City of Elkton on their $4.4 million project.  There was approximately 25 city blocks to rebuild which included the removal and installation of approximately 8,000 feet of sewer main, approximately 8,000 feet of water main, 7,700 ton of asphalt paving, along with all of the services, concrete curb and gutter and street prep.  The project engineer was SPN & Associates in Mitchell, SD.  Bowes Construction of Brookings, SD, Guardrail Enterprises of Chancellor, SD, Hervi Concrete of Willow Lake, SD, Hydro-Klean of Des Moines, IA, Katzer Concrete of Sioux Falls, SD, and Traffic Solutions of Harrisburg, SD were all subcontractors on this project.

Clark Runway 13/31 Reconstruction

  • Halme Inc. was the prime contractor for Clark County to rebuild runway 13/31 at the Clark County Airport.  This was a $1.6 million dollar project that included complete removal of the existing asphalt surfacing as well as 16,000 CUYD of excavation.  The engineer on this project was Helms and Associates in Aberdeen, SD.  Subcontractors included Area, Inc. of Lake Norden, SD, Asphalt Paving and Materials of Huron, SD, Efraimson Electric of Bryant, SD, and Traffic Solutions of Harrisburg, SD.

SDDOT Storm Sewer and Watermain Lowering

  • Halme Inc. was the prime contractor on this joint contract for the SDDOT and Watertown Municipal Utilities.  This $1.6 million dollar project had 5 custom concrete structures, 1,859' of double 42" arch concrete pipe, 632' of 30" concrete pipe, over 3,500 SQYD of concrete flatwork along with asphalt paving and excavation work.  Subcontractors included Brosz Engineering of Sioux Falls, SD, Duininick of Watertown, SD, Efraimson Electric of Bryant, SD, Skyview Construction of Summit, SD, Timmons Construction of Brookings, SD, and Traffic Solutions of Harrisburg, SD.

Past Projects

bottom of page