top of page
YUN00046_edited.jpg

CURRENT PROJECTS

WATER SYSTEM IMPROVEMENTS

CITY OF CLARK, SD

Installation of new 6" watermain pipe, valves, fittings and other appurtenances.

Contract Amount:            $4,682,986.00

Substantial Completion:  7/11/2025

Engineer:                           Helms & Associates, Aberdeen, SD

23RD AVE LIFT STATION

CITY OF MITCHELL, SD

Furnish and install new wet well and valve vault. Remove and dispose of existing lift station.

Contract Amount:            $1,547,214.00

Substantial Completion:  6/15/2025

Engineer:                           SPN & Associates, Mitchell, SD

SANITARY SEWER COLLECTION SYSTEM IMPROVEMENTS PHASE 2

CITY OF AURORA, SD

Furnish and install approximately 5150' of gravity sewer pipe w/ 20 sanitary sewer manholes.

Contract Amount:            $3,683,299.58

Substantial Completion:  11/1/2024

Engineer:                           Banner Associates, Brookings, SD

RIDGEVIEW ON FOSTER IMPROVEMENTS PHASE 1 & 2

MITCHELL AREA DEVELOPMENT CORPORATION

Installation of water, sanitary, and storm sewer, along with excavation, concrete and paving.

Contract Amount:            $2,419,094.13

Substantial Completion:  7/16/2025

Engineer:                           SPN & Associates, Mitchell, SD

CAST IRON WATERMAIN REPLACEMENT

WATERTOWN MUNICIPAL UTILITIES

Removal and replacement of old cast iron pipe with new PVC pipe, valves, fittings, and other appurtenances.

Contract Amount:            $4,292,148.80

Substantial Completion:  9/18/2026

Engineer:                           AE2S, Sioux Falls, SD

3RD STREET WATERLINE PROJECT

CITY OF SUNDANCE, WY

2100' of 10" and 2600' of 8" PVC watermain installation along with fittings, valves, and appurtenances.

Contract Amount:            $2,353,770.00

Substantial Completion:  10/9/2026

Engineer:                           Trihydro Corporation, Lander, WY

EAST WATERMAIN

(NEAR TRENT, SD)

SHARED RESOURCES

36,000' of 20" PVC watermain installed by open trench excavation and directional drilling.  Includes installation of fittings and appurtenances.

Contract Amount:            $5,833,056.20

Substantial Completion:  9/25/2026

Engineer:                           Banner Associates, Brookings, SD

CALUMET AVE AREA & 2ND ST SE UTILITIES

CITY OF DE SMET, SD

Installation of water, sewer, and storm, street reconstruction, concrete, asphalt paving, and sanitary sewer lining.

Contract Amount:            $5,633,771.05

Substantial Completion:  10/31/2026

Engineer:                           IMEG Corp, Aberdeen, SD

LAKE POINSETT LIFT STATION REHABILITATION - 2023

LAKE POINSETT SANITARY DISTRICT

Dewater, reline, remove and replace pumps, controls, etc. on multiple lift stations.

 

Contract Amount:            $853,550.00

Substantial Completion:  5/16/2025

Engineer:                           Banner Associates, Brookings, SD

OHLMAN LIFT STATION

CITY OF MITCHELL, SD

Furnish and install new wet well and valve vault. Remove and dispose of existing lift station.

Contract Amount:            $1,239,223.50

Substantial Completion:  10/15/2025

Engineer:                           SPN & Associates, Mitchell, SD

NORTH HARMON SANITARY SEWER OUTFALL

CITY OF MITCHELL, SD

Furnish and install approx. 2700' of 4", 3500' of 8", 6500' of 12" PVC Sewer Main, and 29 manholes.

Contract Amount:            $3,229,884.25

Substantial Completion:  9/15/2025

Engineer:                           SPN & Associates, Mitchell, SD

MANCHESTER AREA PIPELINE IMPROVEMENTS, PHASE 1

KINGBROOK RURAL WATER SYSTEM

Furnish and install approximately 3700' of 8" PVC water main.

Contract Amount:            $793,900.00

Substantial Completion:  10/31/2024

Engineer:                           DGR Engineering, Rock Rapids, IA

VISTA GRANDE SEWER

CITY OF PINE HAVEN, WY

Installation of grinder pump station, gravity sewer main, manholes and other appurtenances.

Contract Amount:            $243,818.50

Substantial Completion:  7/1/2025

Engineer:                           HDR Engineering, Gillette, WY

DEADWOOD WATER SUPPLY LINE REPLACEMENT

CITY OF LEAD, SD

Installation of approximately 2200' of 8" PVC watermain​ including fittings, valves, pressure reducing valve, and hydrants.

Contract Amount:            $505,722.25

Substantial Completion:  6/1/2025

Engineer:                           Interstate Engineering, Spearfish, SD

PHASE 1 INFRASTRUCTURE IMPROVEMENTS

CITY OF BRYANT, SD

Installation of water, sewer, and storm, along with a new lift station and valve vault.  Also includes concrete and asphalt paving

Contract Amount:            $1,486,300.50

Substantial Completion:  10/31/2025

Engineer:                          IMEG Corp, Aberdeen, SD

STARTING A NEW PROJECT?

Let's Talk. Give us a call or contact us online today to talk about your next project. We are happy to answer any questions you have about our services.

bottom of page